Kitchen Drawer Trash Can Remodel

Order #20231006160131-2230-11-0 · Created October 6, 2023
New Design Fabrication Delivery Complete
Project created Oct 6, 2023 · 9:01 AM
2 weeks slow
Design 1 submitted Oct 19, 2023 · 9:09 PM
by Chris D. McCoy (You3Dit Inc.)
4 minutes
Design 1 approved approx. Oct 19, 2023 · 9:13 PM
by CDM (You3Dit Inc.)
3 minutes
Quote 1 submitted Oct 19, 2023 · 9:16 PM
Chris D. McCoy (You3Dit Inc.) — $195.00/unit via Dewalt 10in Table Saw (15 Amps)
NOW Design approved — ready for quotes
Total elapsed: 2 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.