4 weeks
⚠ bottleneck risk
13 hours
by Chris D. McCoy (You3Dit Inc.)
2 weeks
slow
2 days
2 days
Chris D. McCoy (You3Dit Inc.) — $68.70/unit via Epilog 60W Laser Cutter
1 hour
Chris D. McCoy (You3Dit Inc.)
11 weeks
⚠ bottleneck risk
Sang — $30.00/unit via Creality Cr 10s
Total time: 123 days, 11 hours
Oakland, CA → San Jose, CA
Total elapsed: 18 weeks from project creation to last recorded event.