22 hours
by Chris D. McCoy (You3Dit Inc.)
2 weeks
slow
Chris D. McCoy (You3Dit Inc.) — $36.30/unit via Ultimaker 3 Extended
10 minutes
Chris D. McCoy (You3Dit Inc.) — $18.90/unit via CraftCloud 3D Printing Services
83 weeks
⚠ bottleneck risk
Chris D. McCoy (You3Dit Inc.) — $10.00/unit via Bambu Lab X1-Carbon
40 minutes
6 days
slow
Chris D. McCoy (You3Dit Inc.)
Fabrication — Quote #QT-1535
Chris D. McCoy (You3Dit Inc.) marked parts ready
Total time: 599 days, 15 hours
Bakersfield, CA → Oakland, CA
Total elapsed: 86 weeks from project creation to last recorded event.