Project created Sep 20, 2016 · 7:11 PM
3 hours
Design 1 submitted Sep 20, 2016 · 9:53 PM
by Patrick Owens
11 hours
Design 1 approved approx. Sep 21, 2016 · 9:19 AM
by Patrick Owens
35 minutes
Quote 1 submitted Sep 21, 2016 · 9:54 AM
CDM (You3Dit Inc.) — $0.01/unit via Type A Machines Series 1 Pro
1 week slow
Quote 1 selected approx. Sep 28, 2016 · 1:39 PM
CDM (You3Dit Inc.)
#Sketch2Solid
Total time: 7 days, 18 hours