Projects
›
Pyramid Joint
›
Timeline
Pyramid Joint
Order #20160207200623-366-10-1 · Created February 7, 2016
New
Design
Fabrication
Delivery
Complete
Project created
Feb 7, 2016 · 12:06 PM
1 day
Design 1 submitted
Feb 8, 2016 · 9:13 PM
by John Bruce
3 weeks
⚠ bottleneck risk
Design 2 submitted
Feb 26, 2016 · 11:28 AM
by Chris D. McCoy (You3Dit Inc.)
2 weeks
⚠ bottleneck risk
Design 3 submitted
Mar 13, 2016 · 5:42 PM
by Chris D. McCoy (You3Dit Inc.)
534 weeks idle ⚠
STALLED
Awaiting activity
3741 days without activity
Total elapsed:
5 weeks
from project creation to last recorded event.