Moto Morini Swingarm Spools / Pitbull Stand Bungs / Lift Stand Bobbins

Order #20230912222316-2211-11-0 · Created September 12, 2023
New Design Fabrication Delivery Complete
Project created Sep 12, 2023 · 3:23 PM
1 hour
Design 1 submitted Sep 12, 2023 · 4:37 PM
by Chris D. McCoy (You3Dit Inc.)
Design 1 approved approx. Sep 12, 2023 · 4:38 PM
by CDM (You3Dit Inc.)
14 minutes
Quote 1 submitted Sep 12, 2023 · 4:53 PM
Chris D. McCoy (You3Dit Inc.) — $18.66/unit via Ultimaker 2
5 weeks ⚠ bottleneck risk
Quote 2 submitted Oct 19, 2023 · 12:25 PM
Chris D. McCoy (You3Dit Inc.) — $56.63/unit via Xometry CNC Machining
1 minute
Quote 3 submitted Oct 19, 2023 · 12:27 PM
Chris D. McCoy (You3Dit Inc.) — $83.52/unit via Align Machine Works CNC Turning
1 minute
Quote 2 selected approx. Oct 19, 2023 · 12:28 PM
Chris D. McCoy (You3Dit Inc.)
Quote 3 selected approx. Oct 19, 2023 · 12:28 PM
Chris D. McCoy (You3Dit Inc.)
Quote 1 selected approx. Oct 19, 2023 · 12:28 PM
Chris D. McCoy (You3Dit Inc.)
#Sketch2Solid
Total time: 36 days, 21 hours
Design
15 mins
Total cost
$995.00
Oakland, CA → Gaithersburg, MD
Total elapsed: 5 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.