7 minutes
by Chris D. McCoy (You3Dit Inc.)
2 hours
by Chris D. McCoy (You3Dit Inc.)
2 minutes
by Chris D. McCoy (You3Dit Inc.)
2 hours
27 minutes
Chris D. McCoy (You3Dit Inc.) — $11.59/unit via Zim Hacked Zee Pro
2 weeks
⚠ bottleneck risk
Harding3D — $15.00/unit via Prusa Research Original MK2S
67 weeks
⚠ bottleneck risk
Josh — $10.00/unit via AnyCubic Photon
3 days
Fabrication — Quote #QT-955
Total time: 487 days, 22 hours
Oakland, CA → Grand Rapids, MI
Total elapsed: 70 weeks from project creation to last recorded event.