Habit Keychain

Order #20150720164127-234-10-0 · Created July 20, 2015
New Design Fabrication Delivery Complete
Project created Jul 20, 2015 · 9:41 AM
1 week slow
Design 1 submitted Jul 30, 2015 · 10:08 AM
by Chip Douglas
1 day
Design 2 submitted Jul 31, 2015 · 6:15 PM
by John Bruce
3 days
Design 2 approved approx. Aug 3, 2015 · 10:13 AM
by Sanjeet Sanhotra
NOW Design approved — ready for quotes
Total elapsed: 2 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.