3 minutes
Chris D. McCoy (You3Dit Inc.) — $2.35/unit via Printrbot Simple Metal Plus
17 hours
Conceptual Manufacturing — $8.50/unit via MarkForged Mark Two
1 week
slow
Fabrication — Quote #QT-802
11 weeks
⚠ bottleneck risk
Sang — $6.24/unit via Creality Cr 10s
Total time: 88 days, 12 hours
Oakland, CA → Shailer Park, Queensland
Total elapsed: 13 weeks from project creation to last recorded event.