Forecast - You3Dit Wedgie for MJF

Order #20171214194342-924-11-1 · Created December 14, 2017
New Design Fabrication Delivery Complete
Project created Dec 14, 2017 · 11:43 AM
14 minutes
Design 1 submitted Dec 14, 2017 · 11:57 AM
by CDM (You3Dit Inc.)
12 minutes
Design 2 submitted Dec 14, 2017 · 12:10 PM
by CDM (You3Dit Inc.)
16 minutes
Design 3 submitted Dec 14, 2017 · 12:27 PM
by CDM (You3Dit Inc.)
6 days slow
Design 4 submitted Dec 20, 2017 · 10:25 AM
by CDM (You3Dit Inc.)
1 minute
Design 5 submitted Dec 20, 2017 · 10:27 AM
by CDM (You3Dit Inc.)
28 minutes
Design 6 submitted Dec 20, 2017 · 10:55 AM
by CDM (You3Dit Inc.)
2 hours
Design 7 submitted Dec 20, 2017 · 12:39 PM
by CDM (You3Dit Inc.)
2 days
Design 8 submitted Dec 22, 2017 · 9:52 AM
by CDM (You3Dit Inc.)
1 hour
Design 8 approved approx. Dec 22, 2017 · 11:01 AM
by project owner
2 weeks ⚠ bottleneck risk
Quote 1 submitted Jan 6, 2018 · 3:08 AM
Sinan Toksoz — $100.00/unit via 3D MODEL RAISE 3D N2
16 weeks ⚠ bottleneck risk
Quote 2 submitted Apr 28, 2018 · 5:16 PM
Harding3D — $1.50/unit via Prusa Research Original MK2S
20 weeks ⚠ bottleneck risk
Quote 3 submitted Sep 18, 2018 · 10:24 PM
Nick Petoia — $2.50/unit via Prusa MK3
#Sketch2Solid
Total time: 278 days, 9 hours
Design
22 days, 15 hours
Total cost
$50.00
Total elapsed: 40 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.