For your adventures stencils - etsy

Order #20161016224147-616-11-0 · Created October 16, 2016
New Design Fabrication Delivery Complete
Project created Oct 16, 2016 · 3:41 PM
6 weeks ⚠ bottleneck risk
Design 1 submitted Nov 28, 2016 · 11:29 AM
by CDM (You3Dit Inc.)
Design 1 approved approx. Nov 28, 2016 · 11:29 AM
by CDM (You3Dit Inc.)
#Sketch2Solid
Total time: 42 days, 20 hours
Total cost
$25.00
Total elapsed: 6 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.