Order #20211217023133-1916-11-0 · Created December 16, 2021
NewDesignFabricationDeliveryComplete
Project created
Dec 16, 2021 · 6:31 PM
71 weeks
⚠ bottleneck risk
Design 1 submitted
Apr 30, 2023 · 7:58 PM
by CDM (You3Dit Inc.)
19 weeks
⚠ bottleneck risk
Design 1 approvedapprox.
Sep 7, 2023 · 11:40 AM
by Chris D. McCoy (You3Dit Inc.)
7 minutes
Quote 1 submitted
Sep 7, 2023 · 11:47 AM
CDM (You3Dit Inc.) — $54.11/unit via Ultimaker 2
NOWDesign approved — ready for quotes
Total elapsed: 90 weeks from project creation to last recorded event.