Calibration Cube

Order #20180214184440-991-11-0 · Created February 14, 2018
New Design Fabrication Delivery Complete
Project created Feb 14, 2018 · 10:44 AM
2 days
Design 1 submitted Feb 16, 2018 · 8:52 AM
by CDM (You3Dit Inc.)
Design 1 approved approx. Feb 16, 2018 · 8:52 AM
by Chris D. McCoy (You3Dit Inc.)
10 minutes
Quote 1 submitted Feb 16, 2018 · 9:02 AM
CDM (You3Dit Inc.) — $23.11/unit via Printrbot Simple Metal Plus
48 weeks ⚠ bottleneck risk
Quote 2 submitted Jan 18, 2019 · 3:47 PM
Derek — $35.00/unit via Prusa i3 MK3
NOW Design approved — ready for quotes