Cable Cars Stencil

Order #20150610182640-200-11-1 · Created June 10, 2015
New Design Fabrication Delivery Complete
Project created Jun 10, 2015 · 11:26 AM
9 hours
Design 1 submitted Jun 10, 2015 · 8:40 PM
by Daniel Farbman
2 days
Design 2 submitted Jun 12, 2015 · 8:35 PM
by Chris D. McCoy (You3Dit Inc.)
3 days
Design 3 submitted Jun 15, 2015 · 1:47 PM
by Chip Douglas
2 days
Design 3 approved approx. Jun 17, 2015 · 6:08 PM
by project owner
#Sketch2Solid
Total time: 7 days, 6 hours
Total cost
$10.00
Total elapsed: 1 week from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.