Projects3D GumbyTimeline

3D Gumby

Order #20150528183111-188-01-0 · Created May 28, 2015
New Design Fabrication Delivery Complete
Project created May 28, 2015 · 11:31 AM
2 weeks slow
Quote 1 submitted Jun 8, 2015 · 12:30 PM
Chris D. McCoy (You3Dit Inc.) — $31.00/unit via Printrbot Simple Metal Plus
6 days slow
Quote 1 selected approx. Jun 14, 2015 · 8:41 PM
Chris D. McCoy (You3Dit Inc.)
#Sketch2Solid
Total time: 17 days, 9 hours
Berkeley, CA → Oakand, CA
Total elapsed: 2 weeks from project creation to last recorded event. Events marked approx. use the record's last-modified timestamp — dedicated milestone timestamps will be added in a future update.